Development timelines
Construction of the basketball and athletics stadiums is already underway and will continue through until late 2009.
Construction of the rugby stadium is expected to commence in 2009 and is scheduled for completion in 2010.
An indicative timeframe outlining the key construction milestones is provided below.
|
Site works |
|
|
March 2008 – October 2008 |
Services installation |
|
July 2008 – April 2008 |
Construction of roads and car parking |
|
May 2008 – October 2009 |
Flora corridor weed management and revegetation |
|
|
|
|
Basketball stadium |
|
|
Stadium construction commences |
|
|
March 2008 – November 2009 |
Basement car park construction |
|
April 2008 – June 2009 |
Ground floor construction |
|
October 2008 – June 2009 |
First floor construction |
|
October 2009 |
Opening |
|
|
|
|
Athletics stadium |
|
|
March 2008 |
Stadium construction commences |
|
March 2008 – June 2008 |
Earthworks and forming of track and banks |
|
May 2008 – January 2009 |
Track construction |
|
May 2008 – January 2009 |
Construction of grandstand |
|
April 2009 |
Opening |