Construction of the basketball and athletics stadiums is already underway and will continue through until late 2009.

Construction of the rugby stadium is expected to commence in 2009 and is scheduled for completion in 2010.

An indicative timeframe outlining the key construction milestones is provided below.

Site works

 

March 2008 – October 2008

Services installation

July 2008 – April 2008

Construction of roads and car parking

May 2008 – October 2009

Flora corridor weed management and revegetation

 

 

Basketball stadium

 

March 2008

Stadium construction commences

March 2008 – November 2009

Basement car park construction

April 2008 – June 2009

Ground floor construction

October 2008 – June 2009

First floor construction

October 2009

Opening

 

 

Athletics stadium

 

March 2008

Stadium construction commences

March 2008 – June 2008

Earthworks and forming of track and banks

May 2008 – January 2009

Track construction

May 2008 – January 2009

Construction of grandstand

April 2009

Opening